Client

Yem Technology

Location

Sino Iron Project, Cape Preston, WA

Project

28” Pipe Manifolds

Service

Pressure Piping

Value

Up to $250k

Scope Of Work

3D model drafting, material procurement, fabrication, NDT, sandblast & painting and pack for shipment.

Project Resourcing

Fabrication

  • Required coded welders and boilermakers experienced in piping fabrication.
  • Project Manager provided single point of contact with the client.

Installation

  • Not included – shipping and site installation at Cape Preston by others.
  • Project Achievements
  • APMS provided a comprehensive project management service.
  • All activities were managed to the satisfaction of the client with minimal intervention.

Key Activities

Fabrication

  • Detailed mechanical design to AS1210 and verification
  • 3D modelling and preparation of Autocad drawings
  • Material procurement, including filters
  • Workshop fabrication
  • Coded TIG and FCAW welding to AS3992
  • 100% material and weld traceability
  • Coordination of multiple subcontractors including non- destructive testing (NDT), hydro testing, blasting & painting, logistic arrangements and documentation for shipping.
  • Liaise with the client to ensure Manufacturers Data Report (MDR) contained the information required and drawing updates.